How Long It Actually Takes From Permit to Opening for Public Saunas and Bathhouses in the US
SaunaNews traced 296 US public sauna and bathhouse projects through permits, registries and opening days. A sauna club opens about 11 months after its first building permit filing, a bathhouse or thermal spa about 15 and the biggest spas two years or more. Nearly half missed the first date they announced.